Capital Improvement Projects
MARITIME OFFICE BUILDING DEMOLITION & REFRIGERATED CONTAINER YARD CONVERSION (COMPLETED SUMMER 2020)
This $3.23 million capital project consists of demolishing the Maritime Office Building and transforming the three-acre port-owned property into a large refrigerated container yard.
Once the existing pavement is removed, the awarded contractor, West Construction Inc., will build a heavy duty cargo container rated pavement.
The project also calls for installing new exfiltration trenches and storm piping, new high mast lighting, security fencing, fire protection, underground conduit and infrastructure for future refrigerated container electrical plugs.
In order to convert the property into a container yard, the overhead electrical wiring needs to be relocated underground. A Florida Power and Light certified electrical contractor will install and modify underground utility vaults, electrical transformers and a switchgear.
The new refrigerated container yard will allow our largest tenant to better serve our Caribbean market.
Phase 1 is complete. Phase 2, which includes installation of reefer outlets, is in the works.
Project Progress
Ariel view of the Marine Office Building and parking lot before construction started.
The demolition of the building started in December 2018.
On December 17, 2018, the building was more than half way demolished.
This is what the property look like a month later on January 16, 2019.
This photo was taken in March 2019 during the installation process of the storm drainage system.
Construction of the storm drainage system and electrical underground infrastructure continued into the month of April.
The new refrigerated container yard project progressed into its six month of construction in May. This is when crews began installing the base material for pavement surface.
This photo, taken June 2019, shows the preparation for the new pavement and the start of the installation of electrical equipment inside the power yard.
In early July, crews continued preparing for the installation of the asphalt pavement.
upgrades to mega-yacht berth (COMPLETED JANUARY 2020)
Berth one is located at the north end of the Port of Palm Beach Turning Basin and comprises a bulkhead in north-south direction along the Intercoastal Waterway. The bulkhead was originally constructed in 1976 and consist of anchored steel sheet piling with a reinforced concrete pile cap and facing. Berth One is the only existing bulkhead structure within the Port that has not been replaced since its original construction.
The $4.5 million project consists of replacing approximately 425-feet of sea wall including new bulkhead steel sheet pile installation, tie-backs, concrete cap, marine bollards and fenders. The construction also includes the replacement of a prop-wash wall to match the existing structure.
"This multi-million dollar project took several years in planning and construction. Now that it is open, the Port looks forward to an exciting future with Berth One Palm Beach, the newly named entity leasing this area for accommodations, refitting and repairs to ultra-high value mega yachts that look for a first class experience for their visit to the Palm Beach Area," said Ronald Coddington, Port of Palm Beach Engineer.
A portion of the project included safely relocating corals living on the bulkhead.. Before construction began, the Port of Palm Beach hired a women-owned environment consulting firm, Coastal Eco-Group Inc., to remove stony corals greater than 10 centimeters (cm) in diameter. The corals were relocated to the Town of Palm Beach mitigation reef site. To date, the Port has relocated more than 1,000 corals.